Urea Coater Plant

Project Category: 
Industrial Demolition
Location: 
Redwater, AB
Customer: 
Nutrien

We were contracted to complete the demolition of a redundant Urea Coater Plant within the Nutrien- Redwater Nitrogen Operations in Redwater, Alberta.  Plant 19, standing 29.3m (96ft) at the coater area and within 0.05m (2”) from an active chemical storage facility at the sulphonation section, was demolished using our high reach excavator equipped with a hydraulic shear.

Our crews completed this challenging project as scheduled, without incident and within budget.